The main risk Spiral addresses early is…

Answer options

A
Project-specific major risks (tech, cost, schedule)
B
Grammar errors in docs
C
Color palette selection
D
Keyboard layout

Correct answer: Project-specific major risks (tech, cost, schedule)

Explanation

Risk identification/mitigation governs each spiral.