Close change request
Answer options
A
Evaluate impacts of change request
B
Review stakeholder feedback
C
Analyze the cost of the proposed change
D
Collect impacts of change request
Your answer is correct.
The correct answer is:
Evaluate impacts of change request
Correct answer: Evaluate impacts of change request
Explanation
Closing a change request requires evaluating the impacts of the change — confirming all effects have been assessed and documented before formally closing the request. Option [3] contains the embedded PDF annotation explicitly stating 'The correct answer is: Evaluate impacts of change request', confirming option [0].