Choose the option that accurately represents the sequential order of phases in the Waterfall model.

Answer options

A
Requirement Gathering, Analysis, Design, Implementation, Testing, Deployment, Maintenance
B
Waterfall model
C
Agile model
D
Spiral model

Correct answer: Requirement Gathering, Analysis, Design, Implementation, Testing, Deployment, Maintenance

Explanation

The correct answer is: Requirement Gathering, Analysis, Design, Implementation, Testing, Deployment, Maintenance.